Construction Updates

June 26 - July 2, 2026:

Concrete trucks arrive on site.

June 25 - June 26, 2026:

Caisson drilling occurs over two days.

June 22 - June 25, 2026:

Increased truck traffic due to equipment deliveries and material import.

June 17 - June 25, 2026: 

Demolition and grading activities.

June 11, 2026:

Construction fence installation begins.

June 8, 2026:

Mobilization for construction begins. Potholing and utility locates will occur.

June 3, 2026:

Additional potholing and utility locates will occur.

March 17, 2026:

Potholing to verify utilities will occur on Thursday, March 19 beginning at 7 a.m. and will continue intermittently throughout the day