August 7 - August 24, 2026:

Irrigation installation is underway throughout the project area.

Pond grading is underway.

Underground electrical work is scheduled to begin.

Storm sewer demolition and installation of new storm sewer infrastructure.

July 31 - August 6, 2026:

Backfill and grading around soundwall.

July 24, 2026:

Second concrete pour.

July 17, 2026:

First concrete pour.

July 2 - July 15, 2026:

Forming the sound wall.

June 26 - July 2, 2026:

Concrete trucks arrive on site.

June 25 - June 26, 2026:

Caisson drilling occurs over two days.

June 22 - June 25, 2026:

Increased truck traffic due to equipment deliveries and material import.

June 17 - June 25, 2026: 

Demolition and grading activities.

June 11, 2026:

Construction fence installation begins.

June 8, 2026:

Mobilization for construction begins. Potholing and utility locates will occur.

June 3, 2026:

Additional potholing and utility locates will occur.

March 17, 2026:

Potholing to verify utilities will occur on Thursday, March 19 beginning at 7 a.m. and will continue intermittently throughout the day